The project manager can arrange the project schedule management activities in the following order( )。①Plan Schedule Management ②Define Activities ③Estimate Activity Durations ④Sequence Activities⑤Control Schedule ⑥Develop Schedule
项目经理可以按(①②④③⑥⑤)的顺序安排项目进度管理活动:
①规划进度管理②定义活动③估算活动持续时间④排列活动顺序⑤控制进度⑥制定进度计划。
The IT service manager resigns from a project that meets the scheduleand budget. After hiring an alternativenew manager, the team is opposed to the comments from the new manager. The team is at () developmentstages。
()is closet to Deming's definition of Quality。
The IT service manager has learned that a software canimprove the efficiency of current and future project tasks. Because the software is fresh to the Company. Theengineer is not familiar with the software. The lT service manager decides to send the highest level engineero attend the external training course. The proiect manager uses () risk strategies。
The process control charts are used ()。
Any one or any group of activities utilizing resources totransfer input into output can be viewed as a ()。
( )是在工业和信息化部、国家标准化管理委负会的联合指导下研制的,是我国IT服务行业最佳实践的总结和提升。
国家标准的制定有一套正常程序,分为预阶段、立项阶段、( )阶段、征求意见阶段、审查阶段、批准阶段、( )阶段、复审阶段及废止阶段。