关于进度偏差、成本偏差的描述,不正确的是( )。
本题考查对进度偏差,成本偏差的理解。
SV>0 ,进度超前;SV<0 ,进度滞后;
CV>0,成本节省;CV<0,成本超支;
“项目延期完工时,进度偏差和成本偏差均为零”,应该小于零,故A选项错误。
SV>0 ,SPI>1,进度超前;SV<0 ,SPI<1,进度滞后。
CV>0,CPI>1,成本节省;CV<0,CPI<1,成本超支。
成本控制内容包括:
对造成成本基准变更的因素施加影响;
确保所有变更请求都得到及时处理;
当变更发生时,管理这些变更;
确保成本支出不超过批准的资金限额,阶段性与总额都不超;
监督成本绩效,找出与成本基准的偏差;
对照资金支出,监督工作绩效;
防止出现未经批准的变更;
设法把成本超支控制在可接受范围内。
( )is the process of transforming information so it is unintelligible to anyone but the intended recipient.
As each application module is completed,it undergoes( )to ensure that it operates correctly and reliably.
( )algorithm specifies the way to arrange data in a particular order.
After analyzing the source code,( )generates machine instructions that will carry out the meaning of the program at a later time.
( )can help organizations to better understand the information contained within the data and will also help identify the data that is most important to the business and future business decisions.
浏览器开启无痕浏览模式后,( )依然会被保存下来。
下列协议中,不属于TCP/IP协议簇的是( )。
下列传输介质中,带宽最宽、抗干扰能力最强的是( )。
数控编程常需要用参数来描述需要加工的零件的图形。在平面坐标系内,确定一个点需要2个独立的参数,确定一个正方形需要( )个独立的参数。
某书的页码为1,2,3,...,共用数字900个(一个多位数页码包含多个数字),据此可以推断,该书最大的页码为( )。