下图是一个软件项目的活动图,其中顶点表示项目里程碑,连接顶点的边表示包含的活动,则完成该项目的最少时间为( )天。若活动0->2完成后, 停止(请作答此空)天开始活动2->6,则完成整个项目的最少时间不变。
最少时间就是求项目的关键路径,即所有路径中最长的一条,在该图中路径: 0->2->5->7->8->9=8+15+15+7+10=55是路径最长的。故第一问正确答案为C,55天;第二问其实是计算2->6的松弛时间,即在不影响项目进度的前提下,可推迟开始的时间。本题中2->6在所在路径上的工期是8+20+25=53天,所以松弛时间为55-53=2天;故第二问正确答案为B
( )is the process of transforming information so it is unintelligible to anyone but the intended recipient.
As each application module is completed,it undergoes( )to ensure that it operates correctly and reliably.
( )algorithm specifies the way to arrange data in a particular order.
After analyzing the source code,( )generates machine instructions that will carry out the meaning of the program at a later time.
( )can help organizations to better understand the information contained within the data and will also help identify the data that is most important to the business and future business decisions.
浏览器开启无痕浏览模式后,( )依然会被保存下来。
下列协议中,不属于TCP/IP协议簇的是( )。
下列传输介质中,带宽最宽、抗干扰能力最强的是( )。
数控编程常需要用参数来描述需要加工的零件的图形。在平面坐标系内,确定一个点需要2个独立的参数,确定一个正方形需要( )个独立的参数。
某书的页码为1,2,3,...,共用数字900个(一个多位数页码包含多个数字),据此可以推断,该书最大的页码为( )。