招标文件要求工程的实施期限不得超过20个月,承建单位在投标书内承诺18个月竣工。施工过程中,监理工程师因变更批准顺延工期1个月;综合布线工程露天场地施工中遇到尚未达到合同约定的不可预见外界条件等级的连续降雨,监理工程师为了保证工程质量,指示该部分的施工停工0.5个月。则判定承建单位提前或延误竣工标准的合同工期应为( )个月。
如果是招标选择的承包人,工期总日历天数应为投标书内承包人承诺的天数,不一定是招标文件要求的天数。故本工程初始合同工期为18个月。施工过程中,工程师因变更批准顺延工期1个月,合同工期为19个月。填筑工程施工虽遇到连续降雨,但是未达到合同约定不可预见外界条件等级,因此属于承包人应承担的风险,0.5个月的工期不能顺延。故本题答案应为19个月。
( )is the process of transforming information so it is unintelligible to anyone but the intended recipient.
As each application module is completed,it undergoes( )to ensure that it operates correctly and reliably.
( )algorithm specifies the way to arrange data in a particular order.
After analyzing the source code,( )generates machine instructions that will carry out the meaning of the program at a later time.
( )can help organizations to better understand the information contained within the data and will also help identify the data that is most important to the business and future business decisions.
浏览器开启无痕浏览模式后,( )依然会被保存下来。
下列协议中,不属于TCP/IP协议簇的是( )。
下列传输介质中,带宽最宽、抗干扰能力最强的是( )。
数控编程常需要用参数来描述需要加工的零件的图形。在平面坐标系内,确定一个点需要2个独立的参数,确定一个正方形需要( )个独立的参数。
某书的页码为1,2,3,...,共用数字900个(一个多位数页码包含多个数字),据此可以推断,该书最大的页码为( )。