当前位置:首页 → 计算机类 → 软件水平考试 → 高级信息系统项目管理师->已知某综合布线工程的挣值曲线如下图所示:总预算为1230万元
已知某综合布线工程的挣值曲线如下图所示:总预算为1230万元,到目前为止已支出900万元,实际完成了总工作量的60%,该阶段的预算费用是850万元。按目前的状况继续发展,要完成剩余的工作还需要 ( ) 万元。
根据题干,可判定计算的目标是按当前的CPI来计算剩余工作的预计完工成本。按目前CPI状况继续发展,剩余工作的预计完工成本=(BAC-EV)/CPI,其中BAC=1 230,EV=1230?60%=738,CPI=EV/AC=738/900=0.82。则剩余工作的预计完工成本=(1230-738)/0.82=600
( )is the process of transforming information so it is unintelligible to anyone but the intended recipient.
As each application module is completed,it undergoes( )to ensure that it operates correctly and reliably.
( )algorithm specifies the way to arrange data in a particular order.
After analyzing the source code,( )generates machine instructions that will carry out the meaning of the program at a later time.
( )can help organizations to better understand the information contained within the data and will also help identify the data that is most important to the business and future business decisions.
浏览器开启无痕浏览模式后,( )依然会被保存下来。
下列协议中,不属于TCP/IP协议簇的是( )。
下列传输介质中,带宽最宽、抗干扰能力最强的是( )。
数控编程常需要用参数来描述需要加工的零件的图形。在平面坐标系内,确定一个点需要2个独立的参数,确定一个正方形需要( )个独立的参数。
某书的页码为1,2,3,...,共用数字900个(一个多位数页码包含多个数字),据此可以推断,该书最大的页码为( )。