( )are also known as tally sheets are used to organize facts in a hat will facilitate the effective collection of useful data about all quality problem They are especially useful for gathering attributes let performing inspections to identify defects.
本题解析:
核对表也被称为点检表,用于组织事实,将有助于有效地收集有用的数据,有关质量问题,他们是特别有用的,以收集磨损,执行检查,以确定缺陷。
When required the perform Integrated Change Control Process includes ( ),whichis a formally chartered group responsible for reviewing ting approving deferring or rejecting changes to the project and for conveying and communicating such decisions
本题解析:
当需要时,执行综合变更控制过程包括变更控制委员会(CCB),这是一个正式的特许团体,负责审查批准推迟或拒绝对项目的变更,并负责传达这些决定。
( )describes the configurable items of the project and identifies items that will be recorded and updated so that the product of the project items consistent and operable.
本题解析:
配置管理计划描述项目的可配置项,并标识将被记录和更新的配置项,以使项目的产品保持一致和可操作。
The information security management system preserves the abfidentiality integrity and availability of information by applying a/an( ) management process and gives confidence to interested parties
本题解析:
信息安全管理系统通过应用风险管理过程来保护信息的完整性和可用性,并给予相关方信任。
( )concerns a cycle of organizational activity:the acquisition of information from one or more sources , the custodianship and the distribution of that information to those who need it ,and its ultimate disposition through archiving or deletion.
本题解析:
信息管理涉及组织活动的一个循环:从一个或多个来源采集信息,将信息保存并发布给需要的人,并通过归档或删除进行最终的处置。
( )不适合作为项目监理例会的主要议题。
本题解析:
对于因突发性变更事件引起的进度问题,监理单位应召开紧急协调会议,督促各方采取应急措施赶上进度要求,以便项目的开发能以预期的进度完成。
在监理实施过程中,监理单位与建设单位的联系均以书面函件为准。在不作出紧急处理时可能导致人身、设备或项目事故的情况下,监理应( )。
本题解析:
监理通知与回复
在监理实施过程中,监理单位与建设单位的联系均以书面函件为准。在不做出紧急处理时可能导致人身、设备或项目事故的情况下会先口头或电话通知,事后会在约定时间内补做书面通知。
试卷分类:高级信息系统项目管理师
练习次数:0次
试卷分类:高级系统架构设计师
练习次数:0次
试卷分类:中级系统集成项目管理工程师
练习次数:0次
试卷分类:中级信息系统监理师
练习次数:0次
试卷分类:中级软件设计师
练习次数:0次
试卷分类:高级网络规划设计师
练习次数:0次
试卷分类:高级网络规划设计师
练习次数:0次
试卷分类:高级网络规划设计师
练习次数:0次
试卷分类:中级网络工程师
练习次数:0次
试卷分类:中级网络工程师
练习次数:0次